INFRASTRUCTURE PROJECTS
COMPLETED PROJECTS
PROJECT STATUS
DWS PROJECTS
BUDGET
New Pipeline from Rustfontein to Botshabelo
Modder River: 63mm Ratabane Pipeline Installation
Raw Water Pipeline Cathodic Protection
3 - 4
<
>
The Rustfontein to Lesaka 15km, 700mm ductile Iron pipeline, parallel to the existing 600mm steel pipeline is undergoing testing stages. The project will increase the water supply to the following towns: Botshabelo, Thaba Nchu and Excelsior. The project benefited the community through job creation.
This project was identified because of water shortage at Ratabane and Paradys Villages. The existing pipeline of 75mm diameter stretches from the take-off from the Northern Main Pipeline to Ratabane Village. This was not enough to supply the Ratabane and Paradys Villages; therefore, to augment water supply to the two villages, a 63mm diameter pipeline was installed parallel to the existing pipeline to Ratabane Village. The project benefits the local communities through increased economic activities and job creation, improved water supply to the villages, minimized vandalism and increased revenue for Bloem Water.
2 - 2
<
>
<
2 - 2
>
It was identified that the steel raw water pipeline at Welbedacht Water Treatment Works needed cathodic protection to prevent the pipeline from corroding. The project will repair the pipe coating, prevent the corrosion of the pipeline and extend the lifespan thereof.
No. Project Name Project Description Future Impact Status
Modder River: Borehole Upgrade/Refurbishment
Geophysical investigation underway for 13 villages in Thaba Nchu
Mangaung Metro
North and South of Thaba Nchu villages (15174 beneficiaries)
Geophysical investigation and drilling completed
equipping underway
Bi-directional pipeline between Welbedacht WTW to Knellpoort dam
Remedial action for siltation of Welbedacht Dam by pumping Raw water: Construction of 17 km, Bi- directional Pipe line between Knellpoort Dam and Welbedacht WTW
Mangaung Metro
Bloemfontein, Botshabelo, Thaba Nchu, Dewetsdorp, Wepener
(747 431 beneficiaries)
Kopanong LM
Bethulie, Springfontein, Gariep, Trompsburg
(49 171 beneficiaries)
Design stage
Modder River: Construction of OK-Tabali Pipeline
Construction of 10 km, 600mm diameter pipeline from Tabali Reservoir to OK Reservoirs
Augmentation of Water Supply in the Mangaung Metro
Thaba Nchu (60 696 beneficiaries)
Mantsopa LM (Excelsior)
Design stage completed
Xhariep to Knellpoort pipeline
Construction of 180 km 600 mm diameter pipeline from Xhariep Dam to Existing Bloem Water Infrastructure
Alternative Raw water supply to: Mangaung Metropolitan Municipality, Xhariep District Municipality and Mantsopa Local Municipality: 1.2 million beneficiaries
In Progress – Pre- Feasibility completed, Detailed Feasibility to commence up to Preliminary Designs
Pipeline from Rustfontein WTW to Lesaka Reservoir
Construction of 15 km 700 mm diameter ductile iron
Mangaung Metro
Botshabelo, Thaba Nchu
(747 431 beneficiaries)
Commission, Testing and
Remedial work in progress
Design and Construct Steel bypass line parallel to existing Caledon/BFN PCP line for the 35km from Leeuwkop offtake to Brandkop
Phase 1: Construction of new bypass steel pipeline that is 33.7 km long ,1000 mm diameter pipeline from Leeuwkop junction to Brandkop
Augmentation of Water Supply: Mangaung Metro
Bloemfontein
(747 431 beneficiaries)
Construction in progress
1.
2.
3.
4.
5.
6.
7.
Construction of the 13 km long by 250mm Diameter Dewetsdorp Pipeline
Water supply augmentation in Dewetsdorp Pipeline
Mangaung Metro
Dewetsdorp (9498 beneficiaries)
Construction in progress
The Trompsburg Water Supply-Municipal Water Infrastructure Grant (MWIG)
<
2 - 2
>
The project will increase the water storage capacity for the community of Trompsburg and supply water to the newly constructed regional Albert Nzula Hospital. The Construction of the 3Ml/day reservoir is at sealing stage and the pipe connections have been installed. The construction progress is at 90% of completion. Local communities benefited in terms of job creation, increased water supply and improved storage/water supply to the town and hospital.
BUDGET
Projects
2016/2017
2017/2018
Over/Under
Expenditure
Actual Expenditure
Budget
Over/Under
Expenditure
Actual Expenditure
Budget
R'000
R'000
R'000
R'000
R'000
R'000
R219
million
R61 million
(under expenditure)
R116 million
R177 million
R177 million
(under expenditure)
R41 million
R219
million
R61 million
R116 million
R177 million
R177 million
R41 million
The projects above are multi-year, therefore spending will continue in the next financial year